New Data Center Build Out
Zayo Group brought in Power Solutions to fit out its new 60,000-square-foot data center in Ashburn, VA, providing full electrical infrastructure, switchgear and electrical rooms. Power Solutions also had to excavate around the structure, working around existing underground utilities without interrupting services, as well as provide power distribution to the entire building.
The project additionally required installing four diesel-powered backup generators and a UPS system to ensure uninterrupted power to the 2.5 MW data center.
Over the six-month construction schedule Power Solutions’ team put in almost 19,000 hours to ensure the project stayed on schedule and was completed to the client specifications.